Success story · Logistics

By Reducing Management Losses, We Raised Shipments 27%

In a 12-month transformation at a logistics facility, shop floor management was restructured, employees’ value-adding time increased and daily shipment volume rose 27%; the investment paid back in four months.

Shop floor management, 5S and loading operation transformation at a logistics facility

Real Results Achieved Together

The results came not from adding resources, but from managing the existing operation more effectively.

27%daily shipment increase
4 monthsinvestment payback time
12 monthsproject duration

Gains of the Transformation

  • Employees’ value-adding working time increased
  • Picking and loading workloads were balanced
  • Vehicle waiting and loading traffic was organized
  • A visible, orderly work environment was built with 5S

Starting Point: A Site Without a Common Standard

High performance in logistics operations is not achieved simply with more vehicles or people. Material picking, loading, site traffic and daily management must be organized correctly within the same system.

Daily operations at the facility were not managed with common standards. Untidy site conditions, unbalanced workloads and waiting in vehicle traffic slowed down the shipment process. The main problems were:

  • Unclear management: Shop floor management roles and daily operating standards were missing; operational problems were addressed late.
  • Unbalanced workload: Work distribution in material picking and loading was unbalanced, with non-value-adding movement and waiting.
  • Disorderly traffic and space: Vehicle traffic inside the facility moved irregularly, vehicles waited before loading, and order and visual management were lacking in work areas.

Approach: Shop Floor Management, Workload and Vehicle Traffic Together

The core need was not to use more resources, but to make the existing site organization more orderly and efficient. The work addressed shop floor management, operating standards, workload and vehicle traffic together:

  • The shop floor management organization was restructured; management roles and operational responsibilities were clarified.
  • 5S was implemented across the facility and working standards were defined for daily operations.
  • Material picking and loading activities were analyzed and employee workloads were rebalanced.
  • Non-value-adding movement and waiting were reduced.
  • Vehicle waiting and loading traffic inside the facility was reorganized.
  • A management discipline was established that allows daily performance to be tracked on the shop floor.
5S and daily management discipline on a logistics site
Material picking, loading and vehicle movements began to be managed within the same operational flow.

Result: The Transformation Scorecard

At the end of the twelve-month transformation, daily shipment volume rose 27%; employees’ value-adding working time increased, workloads were balanced and vehicle traffic became more orderly. The project’s payback period was four months.

ParameterBeforeAfterImprovement
Daily shipment volumeBaseline+27%Shipment increase
Value-adding working timeBaselineIncreasedMore efficient work
Vehicle waiting and loading trafficDisorderlyOrderlyLess waiting
Investment payback time–4 monthsFast payback

If you face vehicle waiting, unbalanced workloads or slow picking and loading operations at your facility, let us assess the improvement opportunities together.

Organizing vehicle traffic and loading flow at a logistics facility

Request a Quick Diagnosis on Your Shop Floor

With the Quick Shop Floor Diagnosis, let us analyze your site organization, material flow, employee workloads, vehicle traffic and shipment performance, and build your tailored transformation roadmap together.

Request a quick diagnosis

Explore Our Other Success Stories

35%productivity increase
Industrial Products

35% productivity increase in industrial manufacturing

Four years of lean transformation: the same volume with a smaller workforce.

→
€98,000operational gain in 6 months
Automotive

€98,000 gain in 6 months at an automotive supplier

A lean leadership program made the existing WCM system effective on the shop floor.

→
50%reduction in WIP inventory
White Goods

Smart layout instead of a new building: 50% less WIP inventory

With a flow-based layout, 12 new machines were installed without an additional building investment.

→
39%warehouse capacity recovered
Retail

39% more capacity without enlarging the store warehouse

Product retrieval time in the store warehouse fell from 15 minutes to 5 minutes.

→
82%OEE (up from 65%)
Food

OEE from 65% to 82% in food production

In frozen food production, lead time fell from 10 days to 4.5 days.

→
80%output increase with the same team
Bicycle Manufacturing

Shift output rose from 500 to 900 units with the same team

Line balancing and one-piece flow removed the need for additional staff.

→
70%reduction in WIP inventory
Construction Materials

We fit a 3-floor production facility into 2 floors and cut inventory by 70%

Continuous flow and Kanban raised operational efficiency by 40%.

→
91.2%machine availability
Automotive · TPM

TPM lifted machine availability from 83% to 91.2%

Preventive and autonomous maintenance plus technical skills reduced equipment downtime.

→
76%OEE (up from 65%)
Defense Industry

OEE rose from 65% to 76% in the defense industry

SMED and WIP balancing paid back the investment in two months.

→